Project Progress

Bus Lane night works - 29th May - 15th June

We're working in your area

Lincoln Road - Bus Lane night works

What - Night works for the Lincoln Road Bus Lanes and Watermain Upgrade Project

Why - To install underground services along Lincoln Road including multiple water main crossings, storm water pipeline and power cable ducting for traffic signals.

Where - Lincoln Road between Whiteleigh Ave and Moorhouse Ave.

When - Sunday 29 May until Friday June 15 2022, from 6pm to 7am (weather/site condition dependent).

Contact - The contractor is Isaac Construction. Phone Peter Chum on 03 359 9145 or 027 236 6279 or email Lincolnroad2022@isaac.co.nz, Monday to Friday, 6am to 7pm.

Details:

The contractor will carry out these essential works at night as the areas where the services need to be located are
not accessible during the day when the roads are busier.
There will be a road closure for Bernard Street at the Lincoln Road intersection from 7pm until 6am. Access to
Bernard Street from Lincoln Road will be restricted during this time.
Please see overleaf a map of the overall work area.
For additional information about the Lincoln Road bus lanes project, sign up to receive eNewsletters or find out more
at ccc.govt.nz/lincolnroad. You can also visit isaac.co.nz ‘ongoing projects’ for more specific details about day-to-day
operations and to contact the contractor or report any issues.

Impacts on traffic:

  • Lincoln Road will be open during the work.
  • Temporary traffic management will be set up in the work area. Shoulder closures and stop-go controls will be in place from 7pm as needed.
  • Where road closures on the side streets off Lincoln Road are in place, detour signage will be in installed to direct road users.
  • Temporary bus stops will be installed where existing stops may be affected. Signage will indicate where the bus stop has moved to. Please allow extra time.
  • Cyclists will be merged with the traffic lanes. Please drive with care.
  • Speed will be reduced to 30km/h through the work area.
  • Pedestrian access to footpaths will be maintained at all times with detours in place from time to time. Please follow signage.

Impacts of work:

  • There will be increased noise, dust, and vibration from the use of machinery for activities such as saw cutting, hydro
    excavation, and plate compaction.
  • Most of the work involving noise is planned to be carried out before 11pm where possible.
  • If the work requires a water shut-down a further notice will be provided with dates and times. Please note that all
    planned shut-down will only be carried out at night.
  • On-street parking will be affected on both sides of Lincoln Road where we are working.
  • We will keep work areas small where possible and road cones will indicate where parking will not be available.
  • Property access will be maintained where possible. We will work with businesses and residents during the work.
    Please let us know if you have any specific property access needs e.g. medical visits, home help, large vehicle deliveries or planned works.
Bus Lane Night works
Download PDF
Water Shutdown Notice 30th May

We're working in your area

Lincoln Road - Bus Lane and Watermain Upgrade

We’re planning night work to begin installing the new watermain along Lincoln Road between Monday 30 May until Friday 17 June. At times during this period, we will need to turn the water off. This will take place in sections of the working area. If your water will be affected, there will be a separate notice with specific dates attached to it.

Please see below an example of the water shutdown flyer.

We would like to plan this work to happen at a time that causes the least amount of disruption, particularly to businesses operating in the evenings.

Please fill out this short survey to help us plan the timing of our work. Click Here.

You can also contact Peter Chum on 0272366279 or 03 359 9145 Monday to Friday, 7am to 5pm or email Lincolnroad2022@isaac.co.nz

Water Supply Example
Download PDF
We're Working in your Area - Dickens Street Update 29th May

We're working in your area

Lincoln Road - Bus Lane and Watermain Upgrade

What - Night works for the Lincoln Road Bus Lanes and Watermain Upgrade Project

Why - To install underground services on Lincoln Road including watermain crossings and a stormwater pipeline

Where - Dickens Street at the Lincoln Road Intersection

When - Sunday 29 May until Friday June 17 2022, from 7pm to 6am

Contact - The contractor working on behalf of Christchurch City Council is Isaac Construction Limited. Contact Peter Chum on 0272366279 or 03 359 9145 or email Lincolnroad2022@isaac.co.nz, Monday to Friday, 7am to 5pm.

Details:

  • There will be a one-way system on Dickens Street at the Lincoln Road intersection from 7pm until 6am. Access to Dickens Street from Lincoln Road will be available. Road users needing to access Lincoln Road from Dickens Street will need to detour via the posted detour route.
  • There will be no access to time restricted parking within the workspace area on Dickens Street.
  • Business and property access will be maintained where practicable. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs e.g., medical visits, home help, large vehicles deliveries or planned works
  • Pedestrian detours will be in place at times- please follow signage.
  • Cyclists will need to merge with traffic through the work area. Please follow signage.

Please see below a diagram of the worksite.

Noise: There may be increased noise, dust, and vibrations during work, but it shouldn’t impact on your power, water, gas, or phone services

Safety: Safety is our biggest priority so please keep children and pets away from worksites.

Bins: Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed

Further project information: For more information, you can visit Isaac.co.nz for specific details about the day-to-day operations and to get in touch with the contractor or to report any issues.

Please feel free to get in touch should you have any queries. We appreciate your patience during these works.

Dickens Street
Download PDF
We're Working in your Area - Bernard St Update 29th May

We're working in your area

Lincoln Road - Bus Lane and Watermain Upgrade

What - Night works for the Lincoln Road Bus Lanes and Watermain Upgrade Project

Why - To install underground services along Lincoln Road including multiple watermain crossings, a stormwater pipeline and design the intersection.

Where - Bernard Street at the Lincoln Road intersection

When - Sunday 29 May until Friday June 17 2022, from 7pm to 6am

Contact - The contractor working on behalf of Christchurch City Council is Isaac Construction Limited. Contact Peter Chum on 0272366279 or 03 359 9145 or email Lincolnroad2022@isaac.co.nz, Monday to Friday, 7am to 5pm.

Details:

  • There will be a road closure of Bernard Street at the Lincoln Road intersection from 7pm until 6am. Access to Bernard Street from Lincoln Road will be restricted during this time.
  • There will be no access to time-restricted parking within the workspace area on Bernard Street
  • Business and property access will be maintained where practicable. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs e.g., medical visits, home help, large vehicles deliveries, or planned works
  • Pedestrian detours will be in place at times- please follow signage.
  • Cyclists will need to merge with traffic through the work area. Please follow the signage.

Please see below a diagram of the worksite.

Noise: There may be increased noise, dust, and vibrations during work, but it shouldn’t impact on your power, water, gas, or phone services

Safety: Safety is our biggest priority so please keep children and pets away from worksites.

Bins: Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed

Further project information: For more information, you can visit Isaac.co.nz for specific details about the day-to-day operations and to get in touch with the contractor or to report any issues.

Please feel free to get in touch should you have any queries. We appreciate your patience during these works.

Bernard Street
Bernard Street - Lincoln Road
Download PDF
We're working in your area - Parlane St closure 2nd May - 17th June

We're working in your area

Lincoln Road - bus lane project Parlane St closure

What - We need to extend the road closure of Parlane Street at Lincoln Road where we are working to install the new bus lanes and upgrade the water main in the area.

Why - We have found additional underground services we need to work around, which has delayed our progress. We also are capturing some additional work that is part of our project within the working area.

Where - Lincoln Road between Spencer Street and Dickens Street, Addington.

When - Monday 2 May 2022 to Friday 17 June 2022. Monday to Saturday, 7am to 6pm (weather/site condition dependent). We will update you if any night work is needed to complete this work.

Contact - The contractor working on behalf of Christchurch City Council is Isaac Construction Limited. Contact Peter Chum on 0272366279 or 03 359 9145 or email Lincolnroad2022@isaac.co.nz, Monday to Friday, 7am to 5pm.

Details:

We’re working hard to finish our work on Lincoln Road near Parlane Street so that it can be reopened to residents.

We are expecting to complete this section of work on Friday 17 June but re-open Parlane Street on Friday 10th June.

While we were excavating on Lincoln Road, we discovered additional underground services. We need to plan our work around these, which has slowed progress. It will mean that the closure of Parlane Street will need to be extended, and the detour will remain in place until Friday 10th June.

We’re sorry this work is taking longer than expected. We’ll continue to keep you updated as we complete this stage of work.

This is stage one of works and involves:

  • Closing Parlane Street at the Lincoln Road intersection. This closure will be in place 24 hours a day for the duration of the work. Detours and traffic management will be in place to direct the public around this closure. Please follow signage.
  • Two lanes of traffic will be maintained along Lincoln Road.
  • Parking restrictions will be in place on both sides of Lincoln Road within the working area.
  • Business and property access will be maintained where practicable. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs e.g. medical visits, home help, large vehicle deliveries or planned works.
  • Pedestrian detours will be in place at times - please follow signage.
  • With cyclists merging with traffic where we’re working, we encourage riders to use the Little River Link as an alternative, safer route to Lincoln Road. Cycle detour signage is in place.
Parlane St
Download PDF
UPDATE Start Works Notice 10th May 2022

We're working in your area

Hazeldean Road - Watermain Installation

What - We’re installing a new watermain along Hazeldean Road. As part of this work, Grove Road will be closed between Harman Street and Hazeldean Road. Hazeldean Road will also be one-way eastbound between Lincoln Road and Grove Road.

Why - The ageing watermain is being replaced to create a more reliable network. We are doing this work at the same time we’re installing new priority bus lanes and completing other safety improvement work in the area, to minimise future disruption.

Where - Grove Road (between Harman Street and Hazeldean Road) and Hazeldean Road (between Grove Road and Lincoln Road), Addington. Please refer map below.

When - 25 May to early July 2022. Monday to Saturday, 7am to 6pm (weather/site conditions dependent). We will update you if any night work is needed to complete this work.

Contact - The contractor is Isaac Construction. Phone Peter Chum on 0272366279 or 03 359 9145 or email Lincolnroad2022@isaac.co.nz Monday to Friday, 7am to 7pm.

Details:

This is stage 1.4 of works and is part of a watermain upgrade along the length of Lincoln Road from the Barrington Street/Whiteleigh Avenue intersection, through to Moorhouse Avenue.

All work has been planned in stages to reduce the impact on local businesses and residents, and to keep traffic flowing as best as possible.

Grove Road will be closed from 1 June to 17 June 2022.

Hazeldean Road will be one-way eastbound from 1 June to 1 July 2022. These closures will be in place 24 hours a day for the duration of the works.

Impacts on traffic:

  • A detour will be in place for the Grove Road closure and the Hazeldean Road one-way system. Please follow temporary traffic signage.
  • Cyclists may need to merge with traffic through the work area, and at times may be asked to dismount and use the footpath where cycle lanes are impacted. Please follow signage.
  • Speed will be reduced to 30km/h through the work area.
  • Pedestrian access to footpaths will be maintained at all times with pedestrian detours in place at times. Please follow the signage.

Impacts of work:

  • On-street parking will be affected on both sides of Grove Road inside the closure, and on the west side of Hazeldean Road where we are working.
  • The one-way system on Hazeldean Road will allow traffic to turn off Lincoln Road towards Grove Road.
  • Access to the Hazeldean Business Park off Harman Street will remain at all times with access off Hazeldean Road restricted during the works.
  • We will keep work areas small where possible. Road cones and signage will indicate where parking and driveway access is not available.
  • Property access will be maintained where possible. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs e.g., medical visits, home help, large vehicle deliveries or planned works.
  • There will be increased noise, dust, and vibration from the use of machinery for activities such as saw cutting, hydro excavation, and plate compaction.

Stay Updated:

If you would like to receive updates about the Lincoln Road bus lanes project, sign up to receive eNewsletters or find out more online at ccc.govt.nz/lincolnroad
You can also visit isaac.co.nz ‘ongoing projects’ for more specific details about day-to-day operations, to get in touch with the contractor or to report any issues.


Download PDF
Cycle Route Detour

To avoid roadworks cyclists are encouraged to use a suggested detour via the Little River Link Cycleway. The route is mainly separated from the roadway and runs along quiet, low-speed roads. Follow the detour signage and have a safer ride.

Cycle Route Detour
The suggested cycle detour route
Download PDF
Start Works Notice 20th May 2022

We're working in your area

Lincoln Road - Bus Lane and Watermain Installation

What - Installation of kerb and channel, footpath, and road shoulder works.

Why - This work is part of Stage one of the Lincoln Road bus lane and watermain upgrade project.

Where - 334 Lincoln Road, Entrance to Mountfort Park/Jailhouse Accommodation.

When - Driveway will be closed at various stages on Monday 9 May to Friday 27 May 2022.

Contact - The contractor working on behalf of Christchurch City Council is Isaac Construction Limited. Contact Peter Chum on 0272366279 or 03 359 9145 or email Lincolnroad2022@isaac.co.nz, Monday to Friday, 7am to 5pm.

EXPECT BRIEF DRIVEWAY/ENTRANCE CLOSURES AND RESTRICTED ACCESS AT TIMES DURING THESE WORKS.

Details:

This is Stage 1.2 of works and involves:
• There will be two separate concrete pours to install the new kerb and channel for the Jailhouse Accommodation and Mountfort Park driveway/entrance
• A new footpath and road shoulder will be constructed
• Temporary signalised pedestrian crossing will be installed outside the Comcare building.
• Business and property access will be maintained where practicable. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs e.g., medical visits, home help, large vehicles deliveries or planned works
• Pedestrian detours will be in place at times- please follow signage.

Please see below a diagram of the worksite.

Noise: There may be increased noise, dust, and vibrations during work, but it shouldn’t impact on your power, water, gas, or phone services.

Safety: Safety is our biggest priority so please keep children and pets away from worksites.

Bins: Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.

Further project information: For more information, you can visit Isaac.co.nz for specific details about the day-to-day operations and to get in touch with the contractor or to report any issues.

Please feel free to get in touch should you have any queries. We appreciate your patience during these works.

Lincoln Road Bus Lanes TM Letterdrop Comcare driveway
Download PDF
Start Works Notice 10th May 2022

We're working in your area

Lincoln Road - Watermain Installation

What - We’re installing a new watermain along Hazeldean Road. As part of this work, Grove Road will be closed between Harman Street and Hazeldean Road. Hazeldean Road will also be one-way eastbound between Lincoln Road and Grove Road.

Why - The ageing watermain is being replaced to create a more reliable network. We are doing this work at the same time we’re installing new priority bus lanes and completing other safety improvement work in the area, to minimise future disruption.

Where - Grove Road (between Harman Street and Hazeldean Road) and Hazeldean Road (between Grove Road and Lincoln Road), Addington. Please refer map below.

When - 25 May to 24 June 2022. Monday to Saturday, 7am to 6pm (weather/site conditions dependent). We will update you if any night work is needed to complete this work.

Contact - The contractor is Isaac Construction. Phone Peter Chum on 0272366279 or 03 359 9145 or email Lincolnroad2022@isaac.co.nz Monday to Friday, 7am to 7pm.

Details:

This is stage 1.4 of works and is part of a watermain upgrade along the length of Lincoln Road from the Barrington Street/Whiteleigh Avenue intersection, through to Moorhouse Avenue.
All work has been planned in stages to reduce the impact on local businesses and residents, and to keep traffic flowing as best as possible.
Grove Road will be closed from Wednesday 25 May to Friday 10 June 2022. Hazeldean Road will be one-way eastbound from Wednesday 25 May to Friday 24 June 2022. These closures will be in place 24 hours a day for the duration of the works.

Impacts on traffic:

  • A detour will be in place for the Grove Road closure and the Hazeldean Road one-way system. Please follow temporary traffic signage.
  • Cyclists may need to merge with traffic through the work area, and at times may be asked to dismount and use the footpath where cycle lanes are impacted. Please follow signage.
  • Speed will be reduced to 30km/h through the work area.
  • Pedestrian access to footpaths will be maintained at all times with pedestrian detours in place at times. Please follow the signage.

Impacts of work:

  • On-street parking will be affected on both sides of Grove Road inside the closure, and on the west side of Hazeldean Road where we are working.
  • The one-way system on Hazeldean Road will allow traffic to turn off Lincoln Road towards Grove Road.
  • Access to the Hazeldean Business Park off Harman Street will remain at all times with access off Hazeldean Road restricted during the works.
  • We will keep work areas small where possible. Road cones and signage will indicate where parking and driveway access is not available.
  • Property access will be maintained where possible. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs e.g., medical visits, home help, large vehicle deliveries or planned works.
  • There will be increased noise, dust, and vibration from the use of machinery for activities such as saw cutting, hydro excavation, and plate compaction.

Stay Updated:

If you would like to receive updates about the Lincoln Road bus lanes project, sign up to receive eNewsletters or find out more online at ccc.govt.nz/lincolnroad
You can also visit isaac.co.nz ‘ongoing projects’ for more specific details about day-to-day operations, to get in touch with the contractor or to report any issues.

Hazeldean Road - watermain installation
Download PDF
Start Works Notice 2nd May 2022

We're working in your area

Lincoln Road - Bus Lane and Watermain Upgrade

What - We’re starting work to install the new peak hour bus lanes along both sides of Lincoln Road, between Moorhouse Avenue and Whiteleigh Avenue. As part of this work we need to temporarily close Parlane Street at Lincoln Road.

Why - This work is part of stage one of the Lincoln Road bus lane and watermain upgrade project.

Where - Lincoln Road between Spencer Street and Dickens Street, Addington.

When - 2 May 2022 to 27 May 2022. Monday to Saturday, 7am to 6pm (weather/site condition dependent).

Contact - The contractor is Isaac Construction. Phone Peter Chum on 03 359 9145 or 027 236 6279 or email Lincolnroad2022@isaac.co.nz, Monday to Friday, 7am to 5pm.

Details:

This is stage one of works and involves:

  • Closing Parlane Street at the Lincoln Road intersection from Monday 2 May until Friday 27 May 2022. This closure will be in place 24 hours a day for the duration of the work. Detours and traffic management will be in place to direct the public around this closure. Please follow signage.
  • Two lanes of traffic will be maintained along Lincoln Road.
  • Parking restrictions will be in place on both sides of Lincoln Road within the working area.
  • Business and property access will be maintained where practicable. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs e.g. medical visits, home help, large vehicle deliveries or planned works.
  • Pedestrian detours will be in place at times - please follow signage.
  • Cyclists using Lincoln Road will be asked to merge with motorists through the work area.

For more information please visit Isaac.co.nz ‘ongoing projects’ for specific details about the day-to-day operations and to get in touch with the contractor or to report any issues.




Download PDF
Start Works Notice 1st May 2022

We're working in your area

Lincoln Road - Bus Lane Night Works

What - Night works for locating underground services and investigation works along Lincoln Road, and at the intersections of Clarence Street South, Wise Street and Bernard Street.

Why - In preparation for the Lincoln Road bus lane and watermain upgrade project starting early May 2022. This work has been planned at night to reduce the impact on local businesses and residents, and to keep traffic flowing as much as possible.

Where - Lincoln Road between Clarence Street South and Bernard Street, and Lincoln Road between Clarence
Street South and Moorhouse Avenue, Addington.

When - 1 May 2022 to 5 May 2022. Sunday to Thursday, 6pm to 7am (weather/site condition dependent).

Contact - The contractor is Isaac Construction. Phone Peter Chum on 03 359 9145 or 027 236 6279 or email Lincolnroad2022@isaac.co.nz, Monday to Friday, 7am to 7pm.

Details:

The contractor will carry out these essential works at night as the areas where the services need to be located are not accessible during the day when the roads are busier. This work will provide valuable information to improve the efficiency of the project. For additional information about the Lincoln Road bus lanes project, sign up to receive eNewsletters or find out more at ccc.govt.nz/lincolnroad. You can also visit isaac.co.nz ‘ongoing projects’ for more specific details about day-to-day operations and to contact the contractor or report any issues.

Impacts on traffic:

  • Temporary traffic management will be set up in the work area. Shoulder closures and stop-go controls will be in place from 7pm as needed.
  • Temporary bus stops will be installed where existing stops may be affected. Signage will indicate where the
    bus stop has moved to.
  • Cyclists will be merged with the traffic lanes.
  • Speed will be reduced to 30km/h through the work area.
  • Pedestrian access to footpaths will be maintained at all times with detours in place from time to time. Please follow signage.
  • There will be increased noise, dust, and vibration from the use of machinery for activities such as saw cutting, hydro excavation, and plate compaction.
  • The majority of work involving noise is planned to be carried out before 11pm where possible.
  • On-street parking will be affected on both sides of Lincoln Road where we are working.
  • We will keep work areas small where possible and road cones will indicate where parking will not be available.
  • Property access will be maintained where possible. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs e.g., medical visits, home help, large vehicle deliveries or planned works.

Meet the contractor

We were going to host an online ‘meet the contractor’ webinar on Tuesday 26 April, however due to low
registrations it was cancelled and we recorded the presentation. You can view this online - ccc.govt.nz/lincolnroad.

Lincoln Road - bus lane night works



Download PDF
Start Works Notice 8th April 2022

We’re working in your area

Making Lincoln Road safer for everyone – Stage One

What – We’re installing peak hour bus lanes along both sides of Lincoln Road, between Moorhouse Avenue and Whiteleigh Avenue. We’ll also be making other changes to improve safety for pedestrians, cyclists and drivers.

Why – To create more reliable journey times to get everyone where they want to go on time and to improve safety for all road users.

Where - Lincoln Road between Moorhouse Avenue and Whiteleigh Avenue

When - Monday 2 May 2022 to mid-November 2022. Monday to Saturday, 7am and 6pm. (weather/side condition dependent). We will update you if any night work is needed to complete this work.

Contact – The contractor is Isaac Construction. Phone Peter Chum on 027 236 6279 or 03 359 9199 Monday to Friday, 7am to 7pm.

Details

The new peak hour bus lanes will make bus journey times shorter and more reliable. This is stage one of works, and involves widening Lincoln Road to allow for the bus lanes to be installed. We’ll be making other changes to improve safety for pedestrians, cyclists and drivers. These include:

  • A new pedestrian crossing will be installed by Addington Village, allowing people to cross the road safely
  • Installing new bus stops and shelters
  • Upgrading the Barrington/Whiteleigh Avenue intersection
  • Installing new parking bays
  • Replacing footpaths and water mains
  • Improving street lighting
  • Storm water drainage work
  • Moving kerb and channel and road resurfacing
  • The speed limit on Lincoln Road, between Moorhouse Avenue and Whiteleigh Avenue will be reduced to 30km/h

The bus lanes will operate weekdays between 7am and 9am, towards the city and between 3pm and 6pm towards Halswell.

A bus lane will also be installed on the south side of Moorhouse Avenue, between Selwyn Street and Lincoln Road. This bus lane will only operate between 3pm and 6pm.

During this work

    • We need to dig up parts of the road to complete drainage work and kerb and channel, however we’ll be keeping Lincoln Road open to two-way traffic while we do the work. There will be road closures on several side roads during the work. We will provide updates before any closures take place.
    • All work has been planned in stages to reduce the impact on local businesses and residents, and to keep traffic flowing as best as possible.
    • Temporary bus stops will be installed where existing stops need to be removed.
    • Speed will be reduced to 30km/h through the work area.
    • Rubbish and recycling won’t change. Please continue to but bins out at the usual time for collection.
    • There will be no on-street parking on sections of the road we’re working in. We will keep work areas small where possible.
    • Property access will be maintained where possible. We will work with businesses and residents during the work. Please let us know if you have any specific property access needs eg medical visits, home help, large vehicle deliveries or planned works.
    • The bulk of this work will happen during the day. There will be the occasional time when the contractor will carry out specific tasks at night when the roads are quieter and less congested, or when water connections need to be made. The contractor will give 48 hours notice to affected parties before any night works start.
    • Cycle and pedestrian detours will be in place from time to time – please follow signage.
    • We will be replacing water mains as part of this work. We will update affected residents and businesses when we need to connect to the new water main.

Our team will continue to update you as the project progresses. Please do not hesitate to get in touch if you have any questions or concerns.

Meet the contractor

Due to the current Omicron outbreak, we’re holding an online information session for people wanting to find out more about the project. This will be held on Wednesday 20 April 2022 between 5.30 and 7.30pm.

You can register online by emailing engagement@ccc.govt.nz. A link to register for the webinar will be sent back which needs to be filled out to join. You will have the opportunity to ask questions in the registration as well as in the webinar.

Please let us know by 5pm, Monday 18 April if you would like to attend.

Can’t make this time?

More information about the project, including questions and answers are available online. These will be updated following the online information session. You can view these at ccc.govt.nz/lincolnroad

You are also welcome to phone to talk to us directly about the project on 03 941 8999.

Stay updated

If you would like to receive updates about the Lincoln Road bus lanes project, sign up to receive eNewsletters or find out more online at ccc.govt.nz/lincolnroad

You can also visit isaac.co.nz ‘ongoing projects’ for more specific details about day to day operations and to get in touch with the contractor or to report any issues.

Lincoln Road - bus lanes (stage one) Work area
Work area



Download PDF