Overall project completion (Section 1A & 1B – excluding Lincoln Road work scope) – 99%
*Landscaping to be completed inside the next planting season, from April of this year.
Section 1A
Rose Street/Palmside Intersection – 98% complete
- To complete: Landscaping
Smartlea/Weir Intersection – 98% complete
- To complete: Landscaping
Greenpark/McBeath/Alley to Pablo Place – 98%
- To complete: Landscaping
Pablo Place – 98%
- To complete: Landscaping
Ferniehurst/Woodbank Intersection – 98%
- To complete: Landscaping
Sparks Road – 100%
Greenpark/McBeath – 98%
- To complete: Landscaping
Muirson/McBeath – 98%
- To complete: Landscaping
Molesworth Place – 100%
Ashgrove/Cashmere/Ferniehurst – 98%
- To complete: Landscaping
Section 1B
Domain Terrace overall – 98% complete
Domain Terrace North
- To complete: Landscaping
Domain Terrace South – 96% complete
- To complete: Landscaping and fence re-instatement along Spreydon Domain
Annex Road North – 98% complete
- To complete: Landscaping
Annex Road South – 98% complete
- To complete: Landscaping
Glynne/Cobham/Domain intersection – 98%
- To complete: Landscaping
Lincoln Road – 30% complete
- To asphalt shared path adjacent Lincoln Road
- Install traffic signals and complete work scope
Centennial Park
Centennial Park – 85% complete
- Trenching for new lights – 100% complete
- Light pole installation – 100% complete
- Existing footpath removal – 100% complete
- New asphalt paths – 100%
- Reshape grass berms – 90%
To complete for the park: Line marking, landscaping, signage, hydroseed grass berms