Overall project completion (Section 1A & 1B – excluding Lincoln Road work scope) – 99% complete
*Landscaping to be completed inside the next planting season, from April of this year.
** Snags for the project are currently being completed across the sites, expect to see some of our crews out completing small tasks along the cycleway
Section 1A
Rose Street/Palmside Intersection – 98% complete
- To complete: Landscaping
Smartlea/Weir Intersection – 98% complete
- To complete: Landscaping
Greenpark/McBeath/Alley to Pablo Place – 98% complete
- To complete: Landscaping
Pablo Place – 98% complete
- To complete: Landscaping
Ferniehurst/Woodbank Intersection – 98% complete
- To complete: Landscaping
Sparks Road – 100% complete
Greenpark/McBeath – 98% complete
- To complete: Landscaping
Muirson/McBeath – 98% complete
- To complete: Landscaping
Molesworth Place – 100% complete
Ashgrove/Cashmere/Ferniehurst – 98% complete
- To complete: Landscaping
Section 1B
Domain Terrace overall – 98% complete
Domain Terrace North
- To complete: Landscaping
Domain Terrace South – 96% complete
- To complete: Landscaping and fence re-instatement along Spreydon Domain
Annex Road North – 98% complete
- To complete: Landscaping
Annex Road South – 98% complete
- To complete: Landscaping
Glynne/Cobham/Domain Intersection – 98% complete
- To complete: Landscaping
Lincoln Road – 75% complete
- To asphalt shared path adjacent Lincoln Road
- Install traffic signals and complete work scope
Centennial Park
Centennial Park – 98% complete
- Trenching for new lights – 100% complete
- Light pole installation – 100% complete
- Existing footpath removal – 100% complete
- New asphalt paths – 100% complete
- Reshape grass berms – 100% complete
- To complete for the park: Landscaping