Project Progress

Project Progrress - Week 15 - 21 February 2021

Overall project completion (Section 1A & 1B – excluding Lincoln Road work scope) – 99% complete

*Landscaping to be completed inside the next planting season, from April of this year.

** Snags for the project are currently being completed across the sites, expect to see some of our crews out completing small tasks along the cycleway

Section 1A

Rose Street/Palmside Intersection – 98% complete

  • To complete: Landscaping

Smartlea/Weir Intersection – 98% complete

  • To complete: Landscaping

Greenpark/McBeath/Alley to Pablo Place – 98% complete

  • To complete: Landscaping

Pablo Place – 98% complete

  • To complete: Landscaping

Ferniehurst/Woodbank Intersection – 98% complete

  • To complete: Landscaping

Sparks Road – 100% complete

Greenpark/McBeath – 98% complete

  • To complete: Landscaping

Muirson/McBeath – 98% complete

  • To complete: Landscaping

Molesworth Place – 100% complete

Ashgrove/Cashmere/Ferniehurst – 98% complete

  • To complete: Landscaping

Section 1B

Domain Terrace overall – 98% complete

Domain Terrace North

  • To complete: Landscaping

Domain Terrace South – 96% complete

  • To complete: Landscaping and fence re-instatement along Spreydon Domain

Annex Road North – 98% complete

  • To complete: Landscaping

Annex Road South – 98% complete

  • To complete: Landscaping

Glynne/Cobham/Domain Intersection – 98% complete

  • To complete: Landscaping

Lincoln Road – 75% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope

Centennial Park

Centennial Park – 98% complete

  • Trenching for new lights – 100% complete
  • Light pole installation – 100% complete
  • Existing footpath removal – 100% complete
  • New asphalt paths – 100% complete
  • Reshape grass berms – 100% complete
  • To complete for the park: Landscaping
Project Progress - Week 18 - 24 January 2021

Overall project completion (Section 1A & 1B – excluding Lincoln Road work scope) – 99%

*Landscaping to be completed inside the next planting season, from April of this year.

Section 1A

Rose Street/Palmside Intersection – 98% complete

  • To complete: Landscaping

Smartlea/Weir Intersection – 98% complete

  • To complete: Landscaping

Greenpark/McBeath/Alley to Pablo Place – 98% complete

  • To complete: Landscaping

Pablo Place – 98% complete

  • To complete: Landscaping

Ferniehurst/Woodbank Intersection – 98% complete

  • To complete: Landscaping

Sparks Road – 100% complete

Greenpark/McBeath – 98% complete

  • To complete: Landscaping

Muirson/McBeath – 98% complete

  • To complete: Landscaping

Molesworth Place – 100% complete

Ashgrove/Cashmere/Ferniehurst – 98% complete

  • To complete: Landscaping

Section 1B

Domain Terrace overall – 98% complete

Domain Terrace North

  • To complete: Landscaping

Domain Terrace South – 96% complete

  • To complete: Landscaping and fence re-instatement along Spreydon Domain

Annex Road North – 98% complete

  • To complete: Landscaping

Annex Road South – 98% complete

  • To complete: Landscaping

Glynne/Cobham/Domain intersection – 98% complete

  • To complete: Landscaping

Lincoln Road – 45% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope

Centennial Park

Centennial Park – 95% complete

  • Trenching for new lights – 100% complete
  • Light pole installation – 100% complete
  • Existing footpath removal – 100% complete
  • New asphalt paths – 100% complete
  • Reshape grass berms – 100% complete

To complete for the park: Line marking, landscaping, signage, hydroseed grass berms

Project Progress - Week 11 - 15 January 2021

Overall project completion (Section 1A & 1B – excluding Lincoln Road work scope) – 99%

*Landscaping to be completed inside the next planting season, from April of this year.

Section 1A

Rose Street/Palmside Intersection – 98% complete

  • To complete: Landscaping

Smartlea/Weir Intersection – 98% complete

  • To complete: Landscaping

Greenpark/McBeath/Alley to Pablo Place – 98%

  • To complete: Landscaping

Pablo Place – 98%

  • To complete: Landscaping

Ferniehurst/Woodbank Intersection – 98%

  • To complete: Landscaping

Sparks Road – 100%

Greenpark/McBeath – 98%

  • To complete: Landscaping

Muirson/McBeath – 98%

  • To complete: Landscaping

Molesworth Place – 100%

Ashgrove/Cashmere/Ferniehurst – 98%

  • To complete: Landscaping

Section 1B

Domain Terrace overall – 98% complete

Domain Terrace North

  • To complete: Landscaping

Domain Terrace South – 96% complete

  • To complete: Landscaping and fence re-instatement along Spreydon Domain

Annex Road North – 98% complete

  • To complete: Landscaping

Annex Road South – 98% complete

  • To complete: Landscaping

Glynne/Cobham/Domain intersection – 98%

  • To complete: Landscaping

Lincoln Road – 30% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope

Centennial Park

Centennial Park – 85% complete

  • Trenching for new lights – 100% complete
  • Light pole installation – 100% complete
  • Existing footpath removal – 100% complete
  • New asphalt paths – 100%
  • Reshape grass berms – 90%

To complete for the park: Line marking, landscaping, signage, hydroseed grass berms

Project Progress - Week 23 November - 6 December 2020

Section 1A

Rose Street/Palmside Intersection – 97% complete

  • To complete: Landscaping

Smartlea/Weir Intersection – 97% complete

  • To complete: Landscaping

Greenpark/McBeath/Alley to Pablo Place – 97%

  • To complete: Landscaping

Pablo Place – 97%

  • To complete: Landscaping

Ferniehurst/Woodbank Intersection – 97%

  • To complete: Landscaping

Sparks Road – 90%

  • To complete: Site tidy up, exposed aggregate sections

Greenpark/McBeath – 97%

  • To complete: Landscaping

Muirson/McBeath – 97%

  • To complete: Landscaping

Molesworth Place – 97%

  • To complete: Landscaping

Ashgrove/Cashmere/Ferniehurst – 95%

  • To complete: Landscaping and line marking

Section 1B

Domain Terrace overall – 95% complete

Domain Terrace North

  • To complete: Landscaping and line marking

Domain Terrace South – 95% complete

  • To complete: Landscaping, line marking and fence re-instatement along Spreydon Domain

Annex Road North – 97% complete

  • To complete: Landscaping

Annex Road South – 97% complete

  • To complete: Landscaping

Glynne/Cobham/Domain intersection – 97%

  • To complete: Landscaping

Lincoln Road – 25% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope

Centennial Park

Centennial Park – 65% complete

  • Trenching for new lights – 100% complete
  • Light pole installation – 60% complete
  • Existing footpath removal – 100% complete
  • New path prep – 10%
  • To complete: Complete new path prep, asphalting of new path, site tidy up, install signage
Project Progress - Week 17 - 22 November 2020

Section 1A

Rose Street/Palmside Intersection – 97% complete

  • To complete: Landscaping

Smartlea/Weir Intersection – 97% complete

  • To complete: Landscaping

Greenpark/McBeath/Alley to Pablo Place – 97%

  • To complete: Landscaping

Pablo Place – 97%

  • To complete: Landscaping

Ferniehurst/Woodbank Intersection – 97%

  • To complete: Landscaping

Sparks Road – 70%

  • To complete: Installation of traffic signals, note upcoming night works on Tuesday the 24th of November from 7pm to 11pm

Greenpark/McBeath – 97%

  • To complete: Landscaping

Muirson/McBeath – 95%

  • To complete: Landscaping and line marking.

Molesworth Place – 95%

  • To complete: Kerb reinstatement, landscaping, line marking.

Ashgrove/Cashmere/Ferniehurst – 70%

  • Kerb and channel dig out and prep – 100% complete
  • Footpath prep – 80% complete
  • To complete: Prep and surfacing of footpaths, kerb & channel pour, landscaping, line marking.

Section 1B

Domain Terrace overall – 90% complete

Domain Terrace North

  • Drainage – 100% complete
  • Kerb and channel removal – 100% complete
  • To complete by 27 November: Asphalt footpath, driveways and cycleway, cobblestones across Somers Place landscaping, line marking

Domain Terrace South – 90% complete

  • Drainage – 100% complete
  • Kerb and channel pour – 100% complete
  • Footpath prep 95% complete
  • To complete by 27 November: Complete footpath dig out either side of pinch point and opposite Spreyden Domain, prep and surfacing, landscaping, line marking

Annex Road North – 97% complete

  • To complete: Landscaping

Annex Road South – 97% complete

  • To complete: Landscaping

Glynne/Cobham/Domain intersection – 95%

  • To complete: Landscaping, line marking

Lincoln Road – 25% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope

Centennial Park

Centennial Park – 20% complete

    • Erosion and sediment control installed along edge of river
    • Temporary yard set up
    • Trenching for power for new lights – 60% complete
    • Existing footpath removal – 20% complete
Project Progress - Week 9 - 16 November 2020

Section 1A

Rose Street/Palmside Intersection – 97% complete

  • To complete: Landscaping

Smartlea/Weir Intersection – 97% complete

  • To complete: Landscaping

Greenpark/McBeath/Alley to Pablo Place – 97%

  • To complete: Landscaping

Pablo Place – 97%

  • To complete: Landscaping

Ferniehurst/Woodbank Intersection – 97%

  • To complete: Landscaping

Sparks Road – 70%

  • To complete: Installation of traffic signals, note upcoming night works on Tuesday the 24th of November from 7pm to 11pm

Greenpark/McBeath – 97%

  • To complete: Landscaping

Muirson/McBeath – 90%

  • Removal of existing kerb and channel – 100% complete
  • Prep for new kerb and channel – 100% complete
  • Kerb and channel installed – 100%
  • Drainage upgrade – 100% complete
  • Carriageway dig out – 100% complete
  • Cobblestone intersections – 100% complete
  • To complete: Asphalting McBeath Avenue portion of the intersection 19th of November 2020, landscaping, line marking.

Molesworth Place – 70%

  • Prep for new kerb and channel – 100% complete
  • Drainage upgrade – 100% complete
  • Installation of cobble threshold 18th of November 2020

Ashgrove/Cashmere/Ferniehurst – 50%

  • Kerb and channel dig out and prep – 100% complete
  • Footpath prep – 60% complete
  • To complete: Prep and surfacing of footpaths, landscaping, linemarking

Section 1B

Domain Terrace overall – 87% complete

Domain Terrace North

  • Drainage – 100% complete
  • Kerb and channel removal – 100% complete
  • To complete by 27th of November 2020: Complete the remaining kerb and channel pour opposite Medical Centre, asphalt of footpath, driveways and cycleway, landscaping, line marking

Domain Terrace South – 87% complete

  • Drainage – 100% complete
  • Kerb and channel removal – 100% complete
  • Kerb and channel pour – 90% complete
  • Footpath prep 95% complete
  • To complete by 27th of November 2020: Remaining kerb and channel prep and pour, complete footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North – 97% complete

  • To complete: Landscaping

Annex Road South – 95% complete

  • To complete by 16th of November 2020: Small section of footpath to be prepped and sealed, landscaping

Glynne/Cobham/Domain intersection – 95%

  • To complete: Landscaping, line marking

Lincoln Road – 25% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope

Centennial Park

Centennial Park – 15% complete

  • Erosion and sediment control installed along edge of river
  • Temporary yard set up
  • Trenching for power for new lights
Project Progress - Week 1 - 8 November 2020

Section 1A

Rose Street/Palmside Intersection – 97% complete

  • To complete: Landscaping

Smartlea/Weir Intersection – 97% complete

  • To complete: Landscaping

Greenpark/McBeath/Alley to Pablo Place – 97%

  • To complete: Landscaping

Pablo Place – 97%

  • To complete: Landscaping

Ferniehurst/Woodbank Intersection – 97%

  • To complete: Landscaping

Sparks Road – 70%

  • To complete: Installation of traffic signals, note upcoming night works – date to be advised via work notice update

Greenpark/McBeath – 97%

  • To complete: Landscaping

Muirson/McBeath – 75%

  • Removal of existing kerb and channel – 100% complete
  • Prep for new kerb & channel – 100% complete
  • Kerb & channel installed – 100%
  • Drainage upgrade – 100% complete
  • Carriageway dig out – 75% complete
  • To complete: Carriageway dig out, prep, new surfacing of intersection, landscaping, line marking.

Molesworth Place – 25%

  • Removal of existing kerb & channel
  • Prep for new kerb & channel
  • Drainage upgrade

Section 1B

Domain Terrace overall – 85% complete

Domain Terrace North

  • Drainage – 100% complete
  • Kerb and channel removal – 100% complete
  • To complete by 27 November: Complete the remaining kerb & channel pour opposite Medical Centre, asphalt of footpath, driveways and cycleway, landscaping, line marking

Domain Terrace South – 85% complete

  • Drainage – 100% complete
  • Kerb and channel removal – 100% complete
  • Kerb and channel pour – 90% complete
  • Footpath prep 95% complete
  • To complete by 27 November: Remaining kerb & channel prep and pour, complete footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North – 97% complete

  • To complete: Landscaping

Annex Road South – 95% complete

  • To complete by 16 November: Small section of footpath to be prepped and sealed, landscaping

Glynne/Cobham/Domain intersection – 95%

  • To complete: Landscaping, line marking, work scope off Glynne Crescent to Smartlea Bridge

Lincoln Road – 25% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope

Centennial Park

Centennial Park – 5% complete

  • Erosion and sediment control installed along edge of river
  • Temporary yard set up
Project Progress - Week 26 - 31 October 2020

Section 1A

Rose Street/Palmside Intersection – 95% complete

  • To complete: Line marking and landscaping

Smartlea/Weir Intersection – 95% complete

  • To complete: Line marking and landscaping

Greenpark/McBeath/Alley to Pablo Place – 95%

  • To complete: Line marking and landscaping

Pablo Place – 95%

  • To complete: Line marking and landscaping

Ferniehurst/Woodbank Intersection – 90%

  • Road dig out and prep 90% complete
  • Block paving 100% complete
  • To complete: Sealing, landscaping, line marking

Sparks Road – 70%

  • To complete: Installation of traffic signals, note upcoming night works – date to be advised via work notice update

Greenpark/McBeath – 95%

  • To complete: Landscaping, line marking

Muirson/McBeath – 55%

  • Removal of existing kerb and channel – 100% complete
  • Prep for new kerb & channel – 100% complete
  • Kerb & channel installed – 100%
  • Drainage upgrade – 100% complete
  • Carriageway dig out started
  • To complete: Carriageway dig out, prep, new surfacing of intersection, landscaping, line marking.

Molesworth Place – 10%

  • Removal of existing kerb & channel started

Section 1B

Domain Terrace overall – 80% complete

Domain Terrace North

  • Drainage – 100% complete
  • Kerb and channel removal – 100% complete
  • To complete by 27 November: New kerb & channel to be installed, footpath/cycleway prep and surfacing, paving, landscaping, line marking

Domain Terrace South – 75% complete

  • Drainage 100% complete
  • Kerb and channel removal 100% complete
  • Footpath dig out 85% complete
  • To complete by 27 November: Remaining kerb & channel prep and pour, complete footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North – 95% complete

  • To complete by 16 November: Line marking, complete work scope at Linden Grove/Mokihi Gardens/Annex Road roundabout week ending 8/11/2020

Annex Road South – 95% complete

  • To complete by 16 November: Complete asphalting at Lincoln Road end, landscaping and line marking

Glynne/Cobham/Domain intersection – 90%

  • Kerb and channel – 100% complete
  • Footpaths prepped and asphalted – 100% complete
  • To complete: Shoulder reconstruction, landscaping, line marking, work scope off Glynne to Smartlea Bridge

Lincoln Road – 25% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope
Project Progress - Week 19 - 25 October 2020

Section 1A

Rose Street/Palmside Intersection – 95% complete

  • To complete: Line marking and landscaping

Smartlea/Weir Intersection – 95% complete

  • To complete: Line marking and landscaping

Greenpark/McBeath/Alley to Pablo Place – 95%

  • To complete: Line marking and landscaping

Pablo Place – 95%

  • To complete: Line marking and landscaping

Ferniehurst/Woodbank Intersection – 75%

  • Road dig out and prep 80% complete
  • Block paving 60% complete
  • To complete: Backfill and block paving, lowering of manhole, sealing, landscaping, line marking

Sparks Road – 70%

  • To complete: Installation of traffic signals, note upcoming night works – date to be advised via work notice update

Greenpark/McBeath – 95%

  • To complete: Landscaping, line marking

Muirson/McBeath – 25%

  • Removal of existing kerb and channel started
  • Prep for new kerb & channel
  • Drainage upgrade started
  • Carriageway dig out started
  • To complete: Kerb and channel pour, drainage upgrade work, carriageway dig out, prep, new surfacing of intersection, landscaping, line marking.

Section 1B

Domain Terrace overall – 75% complete

Domain Terrace North

    • Drainage 97% complete
    • Kerb and channel removal – 85% complete
    • To complete by 26 October: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Domain Terrace South – 70% complete

  • Drainage 100% complete
  • Kerb and channel removal 100% complete
  • Footpath dig out 85% complete
  • To complete by 26 October: Kerb and channel prep and pour, complete footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North – 95% complete

  • To complete by 26 October: Sealing of road shoulder and remaining shared path (28/10/2020), line marking, complete work scope at Linden Grove/Mokihi Gardens/Annex Road roundabout

Annex Road South – 95% complete

  • To complete by 26 October: Build out, complete asphalting at Lincoln Road end, landscaping and line marking

Glynne/Cobham/Domain intersection – 80%

  • Kerb and channel installed
  • Footpaths prepped and asphalted
  • To complete: Shoulder reconstruction, landscaping, line marking

Lincoln Road – 25% complete

  • To asphalt shared path adjacent Lincoln Road
  • Install traffic signals and complete work scope
Project Progress - Week 5 - 11 October 2020

Section 1A

Rose Street/Palmside Intersection – 95% complete

  • To complete: Line marking and landscaping to be completed by 25 October 2020

Smartlea/Weir Intersection – 95% complete

  • To complete: Line marking and landscaping by 25 October 2020

Greenpark/McBeath/Alley to Pablo Place – 85%

  • Footpaths and carriageway prepared and sealed on southern side
  • New kerb and channel installed
  • To complete: chip seal and footpath construction on northern side of Greenpark Street, landscaping, line marking

Pablo Place – 70%

  • To complete: Asphalting of new footpaths, landscaping, line marking

Ferniehurst/Woodbank Intersection – 65%

  • Kerb and channel complete
  • Road dig out and prep 70% complete
  • To complete: Prep for new footpaths, block paving, traffic flip to other side of intersection (Stage 2 of construction as per start work notice)

Sparks Road – 70%

  • To complete: Installation of traffic signals, note upcoming night works – date to be advised via work notice update

Greenpark/McBeath – 25%

  • Remove existing kerb and channel
  • Prep for new kerb and channel
  • Remove existing chip seal, dig out and prep for block paving complete
  • To complete: seal carriageway, landscaping, line marking, asphalt footpaths

Section 1B

Domain Terrace overall – 55% complete

Domain Terrace North

  • Drainage 90% complete
  • Kerb and channel removal – 75% complete
  • To complete by 26 October 2020: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Domain Terrace South

  • Drainage 100% complete
  • Kerb and channel removal – 75% complete
  • To complete by 26 October 2020: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North – 90% complete

  • Trenching completed
  • Kerb and channel 90% installed
  • Dig out and prep for footpaths 95% complete
  • Started landscaping
  • To complete by 26 October 2020: asphalt laid, chip seal carriageway, line marking, complete work scope at Linden Grove/Mokihi Gardens/Annex Road roundabout

Annex Road South – 90% complete

  • Dig out and prep for remaining footpaths
  • Prep for new footpath 85% complete
  • To complete by 26 October 2020: Complete footpath dig out, prep and asphalt surfacing, block paving at Lincoln Road/Annex Road intersection starting 28/09/2020, landscaping, line marking

Glynne/Cobham/Domain intersection – 50%

  • Kerb and channel dig out and prep
  • Kerb and channel pour 12 October 2020
  • Existing footpath to be stripped, prepped and new seal put down
Project Progress - Week 28 September - 4 October 2020

Section 1A

Rose Street/Palmside Intersection – 95% complete

  • All drainage installed
  • All kerb and channel placed
  • Footpaths asphalted and block paving placed
  • Carriageway constructed
  • Island installed
  • To complete: Line marking and landscaping to be completed by 25/10/20

Smartlea/Weir Intersection – 95% complete

  • All drainage installed
  • All kerb and channel placed
  • Block paving installed on McBeath Avenue
  • Carriageway prep and surfacing complete
  • To complete: Line marking and landscaping by 25/10/20

Greenpark/McBeath/Alley to Pablo Place – 85% complete

  • Drainage installed
  • Footpaths and carriageway prepared and sealed on southern side
  • Kerb and channel 80% complete
  • To complete: Remaining kerb and channel on northern side of Greenpark Street, landscaping, line marking

Pablo Place – 30% complete

  • Dig out of existing kerb and channel
  • Dig out of road shoulder and footpaths
  • Drainage complete
  • Prep and pour new kerb and channel
  • Prep new shoulder
  • To complete: Asphalting of new footpaths, sealing on road shoulder, landscaping, line marking

Ferniehurst/Woodbank Intersection – 55% complete

  • Prep for kerb and channel
  • Drainage complete
  • Road dig out and prep 70% complete
  • To complete: Prep for new footpaths, complete dig out and prep for carriageway, block paving, traffic flip to other side of intersection (Stage 2 of construction as per start work notice)

Sparks Road – 50% complete

  • Dig out of existing kerb and channel
  • Prep and pour of new kerb and channel
  • Started to install traffic signals
  • To complete: Installation of traffic signals, note upcoming night works now planned for the 11th of October – start work notice to follow

Greenpark/McBeath – 25% complete

  • Remove existing kerb and channel
  • Prep for new kerb and channel
  • Remove existing chip seal
  • To complete: dig out and prep for block paving, landscaping, line marking, footpaths

Section 1B

Domain Terrace overall – 40% complete

Domain Terrace North

  • Drainage 50% complete
  • To complete by 26 October: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Domain Terrace South

  • Drainage 100% complete
  • To complete by 26 October: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North – 85% complete

  • Trenching completed
  • Kerb and channel 90% installed
  • Dig out and prep for footpaths 85% complete
  • Started landscaping
  • To complete by 26 October: remaining kerb and channel to be installed, remaining footpaths to be dug out, prepped and asphalt laid, chip seal carriageway, line marking, complete work scope at Linden Grove/Mokihi Gardens/Annex Road roundabout

Annex Road South – 70% complete

  • Dig out and prep for remaining footpaths
  • Prep for new footpath 85% complete
  • To complete by 26 October: Complete footpath dig out, prep and asphalt surfacing, block paving at Lincoln Road/Annex Road intersection starting 28/09/2020, landscaping, line marking

Glynne/Cobham/Domain intersection – 30% complete

  • Mobilisation into site, start potholing
  • Kerb and channel dig out and prep
Project Progress - Week 21 - 27 September 2020

Section 1A

Rose Street/Palmside Intersection – 95% complete

  • All drainage installed
  • All kerb and channel placed
  • Footpaths asphalted and block paving placed
  • Landscaping complete
  • Carriageway constructed
  • Island installed
  • To complete: Line marking to be completed by 25 September 2020

Smartlea/Weir Intersection – 85% complete

  • All drainage installed
  • All kerb and channel placed
  • Block paving installed on McBeath Avenue
  • Carriageway prep complete
  • To complete by 28 September 2020: block paving of Smartlea Street, asphalt footpaths, landscaping, line marking

Greenpark/McBeath/Alley to Pablo Place – 75%

  • Drainage installed
  • Footpaths and carriageway prepared
  • Kerb and channel 60% complete
  • To complete by 28 September 2020: Remaining kerb and channel, asphalt footpaths and alley way, landscaping, line marking

Pablo Place – 10%

  • Dig out of existing kerb and channel
  • Dig out of road shoulder and footpaths

Ferniehurst/Woodbank Intersection – 16%

  • Prep for kerb and channel
  • Drainage underway

Section 1B

Domain Terrace North

  • Drainage 50% complete
  • To complete by 26 October 2020: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Domain Terrace South

  • Drainage 95% complete
  • To complete by 26 October 2020: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North – 75% complete

  • Trenching completed
  • Kerb and channel 80% installed
  • Dig out and prep for footpaths 65% complete
  • Started landscaping
  • To complete by 26 October 2020: remaining kerb and channel to be installed, remaining footpaths to be dug out, prepped and asphalt laid, chip seal carriageway, line marking, complete work scope at Linden Grove/Mokihi Gardens/Annex Road roundabout

Annex Road South – 60% complete

  • Existing footpath dig out (reserve and parallel to Lincoln Road)
  • Prep for new footpath 85% complete
  • To complete by 26 October 2020: Complete footpath dig out, prep and asphalt surfacing, block paving at Lincoln Road/Annex Road intersection starting 28 September 2020, landscaping, line marking

Glynne/Cobham/Domain intersection – 0%

  • Mobilisation into site, start potholing
Project Progress - Week 14 - 20 September 2020

Section 1A

Rose Street/Palmside Intersection

  • All drainage installed
  • All kerb and channel placed
  • Prepping for footpaths to be asphalted
  • Carriageway construction
  • Island installed
  • To complete by 14 September: Block paving on footpath, asphalting, landscaping, line marking

Smartlea/Weir Intersection

  • All drainage installed
  • McBeath Ave kerb and channel placed
  • Block paving installed on McBeath Avenue
  • To complete by 21 September: carriageway dig out, prep, block paving, Weir Place kerb and channel, asphalt footpaths, landscaping, line marking

Greenpark/McBeath/Alley to Pablo

  • Drainage installed
  • Prep for footpaths
  • To complete by 21 September: Install kerb and channel, asphalt footpaths and alley way, landscaping, line marking

Section 1B

Domain Terrace North

  • Drainage 25% complete
  • To complete by 26 October: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Domain Terrace South

  • Drainage 80% complete
  • To complete by 26 October: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North

  • Trenching completed
  • Kerb and channel 80% installed
  • Dig out and prep for footpaths 65% complete
  • To complete by 26 October: remaining kerb and channel to be installed, remaining footpaths to be dug out, prepped and asphalt laid, landscaping, line marking, complete work scope at Linden Grove/Mokihi Gardens/Annex Road roundabout

Annex Road South

  • Existing footpath dig out (reserve and adjacent to Lincoln Road)
  • Prep for new footpath
  • To complete by 26 October: Complete footpath dig out, prep and asphalt surfacing, block paving at Lincoln Road/Annex Road intersection, landscaping, line marking
Project Progress - Week 12 - 18 October 2020

Section 1A

Rose Street/Palmside Intersection – 95% complete

  • To complete: Line marking and landscaping to be completed by 25/10/20

Smartlea/Weir Intersection – 95% complete

  • To complete: Line marking and landscaping by 25/10/20

Greenpark/McBeath/Alley to Pablo Place – 95%

  • To complete: Line marking and landscaping by 2/11/2020

Pablo Place – 95%

  • To complete: Line marking and landscaping by 2/11/2020

Ferniehurst/Woodbank Intersection – 65%

  • Kerb and channel complete
  • Road dig out and prep 70% complete
  • Block paving 60% complete
  • Prep for footpaths complete
  • To complete: Traffic flip to other side of intersection (Stage 2 of construction as per start work notice) to enable remaining dig out, backfill and block paving, lowering of manhole, sealing, landscaping, line marking

Sparks Road – 70%

  • To complete: Installation of traffic signals, note upcoming night works – date to be advised via work notice update

Greenpark/McBeath – 95%

  • Chip sealing of carriageway complete 19/10/2020
  • To complete: Landscaping, line marking

Muirson/McBeath – 5%

  • Removal of existing kerb and channel started
  • To complete: Kerb and channel dig out, drainage upgrade work, carriageway dig out, prep, install new kerb and channel, new surfacing of intersection, landscaping, line marking.

Section 1B

Domain Terrace overall – 55% complete

Domain Terrace North

  • Drainage 95% complete
  • Kerb and channel removal – 85% complete
  • To complete by 26 October: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Domain Terrace South

  • Drainage 100% complete
  • Kerb and channel removal – 85% complete
  • To complete by 26 October: Kerb and channel, footpath dig out, prep and surfacing, paving, landscaping, line marking

Annex Road North – 95% complete

  • Started landscaping scope
  • To complete by 26 October: line marking, complete work scope at Linden Grove/Mokihi Gardens/Annex Road roundabout

Annex Road South – 95% complete

  • To complete by 26 October: Landscaping and line marking

Glynne/Cobham/Domain intersection – 70%

  • Kerb and channel installed
  • Footpaths prepped and asphalted
  • To complete: Shoulder reconstruction, landscaping, line marking

Existing Sites

Sparks Road – Night Works Update - 24 November 2020

What: Traffic light installation

Where: Between 35 and 60 Sparks Road

When: Tuesday 24 November between the hours of 7pm and 11pm – night works

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • From 7pm to 11pm on Tuesday 24 November, traffic will be reduced to one lane under stop-go control.
  • Work will involve the use of a concrete saw which will have the biggest noise impact and this will be from 7pm until 9pm (at the latest). Following this, the work will have a low level of noise disruption for residents.
  • Residents will have access to their driveways, however if there is a short period where we have to restrict access, our supervisor will discuss individual access needs with affected residents directly.
Download PDF
Lincoln Road to Cobham Street: 19 October 2020

What: Two-way lane shift, temporary footpaths, cyclist merging, 30kmph

Where: From Lincoln Road to Cobham Street

When: Monday, August 24th from 7am to Friday 27th November 6pm

Why: To enable the construction of the Nor’West Arc cycleway on behalf of CCC.

Traffic Impacts

  • This update to the current work notice is to advise residents that our work programme has been extended through to the 27th of November due to a number of unforeseen circumstances that arose during the first phase of the upgrade work along Domain Terrace.
  • We will continue to maintain pedestrian access where possible, with alternative routes clearly marked where applicable.
  • We will continue to maintain residents’ access where possible as we work predominantly on the western side of Domain Terrace constructing the shared path.
  • We appreciate there is a lot of construction going on in the area and our crews are working hard to minimise the duration of our disruption in the area.
Download PDF
Ashgrove Terrace / Ferniehurst Street / Molesworth Place / Ferniehurst Bridge Intersection: 19 October 2020

What: Footpath, kerb and channel, road construction, landscaping – including block paving

Where: Intersection of Ferniehurst Street and Ashgrove Terrace and Molesworth Place

When: Monday, 26th October to Monday 30th November – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc Cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Please note we will make a start on Molesworth Place from the 26th of October, this will not impact residents’ access to Molesworth Place, access will be maintained via 1 or 2 lanes – depending on our work scope.
  • Our work on the Ferniehurst Bridge will start from the 2nd of November, once the Woodbank-Ferniehurst intersection upgrade work is complete.
  • Access to Cashmere Road via the Ferniehurst Bridge will be temporarily closed.
  • Ferniehurst Street, between Molesworth Place and Ashgrove Terrace will also be temporarily closed.
  • There will be some minor works undertaken on the corner of Molesworth Place and Ferniehurst Street. Two lanes for traffic will be maintained for the duration of the works.
  • Ashgrove Terrace will be reduced to one lane, controlled by traffic lights either side of the bridge to enable the upgrade works.
  • Detours will be in place for Ashgrove residents via Ashgrove Terrace, Fairview Street and then onto Cashmere Road.
  • Detours for Molesworth Place, Ferniehurst Street, Woodbank Street, Karaka Place, Paikea Place and Palmside Street will be via Palmside Street, Rose Street, Hoon Hay Road and back onto Cashmere Road.
  • Pedestrian access will be maintained but may change on a day to day basis, depending on works.
Download PDF
Domain Terrace and Edinburgh Street Intersection: 19 October 2020

What: Footpath, kerb and channel, road construction, landscaping

Where: Intersection of Domain Terrace and Edinburgh Street

When: Monday, 19th October to Saturday 24th October – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc Cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Temporary road closure from #86 to #88 Domain Terrace to #8 Edinburgh Street up to the intersection.
  • Domain Terrace will still have a two lane diversion in place in conjunction with the intersection closure.
  • The intersection closure will impact Domain Terrace residents who will need to detour via:
  1. Domain Terrace residents on the northern side of the intersection, detour via Lincoln Road.
  2. Domain Terrace residents on the southern side of the intersection, detour via Neville Street and onto Lyttleton Street
  • Please note, pedestrian access will be maintained but may change on a day to day basis depending on the works.
  • Between the hours of 7am and 6pm, residents requiring access to their properties where there is no designated pedestrian walkway will be escorted by a crew member to ensure a safe entry/exit to and from their properties.
Download PDF
Domain Terrace: 19 October 2020

What: Footpath, kerb and channel, road construction, landscaping

Where: Domain Terrace – between property #70 and property #80

When: Tuesday, 27th October to Sunday, 8th November – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc Cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Temporary road closure from #86 to #88 Domain Terrace and #8 Edinburgh Street to intersection.
  • Domain Terrace will still have a 2 lane diversion in place in conjunction with the intersection closure.
  • The closure will impact:
  1. Domain Terrace residents on the west side of intersection are to detour via Lincoln Road
  2. Domain Terrace residents on the east side of intersection are to detour via Neville Street – Lyttleton Street.
  • Please note, pedestrian access will be maintained but may change on a day to day basis, depending on works. Inside the hours of 7am – 6pm, residents requiring access to their properties where there is no designated pedestrian walkway will be escorted by a crew member to ensure a safe entry/exit to and from their properties.
Download PDF
Centennial Park – from Rose Street to Sparks Road - 26 October 2020

What: Footpath, cycleway, shared path construction, installation of lighting for new path, landscaping

Where: Along existing path alignment through Centennial Park, from Rose Street to Sparks Road

When: Monday 2 November to Friday 18 December – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc Cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Impact for Park Users

  • Full closure of the existing footpath from Rose Street to Sparks Road.
  • A temporary yard will be situated at the Rose Street end of the park.
  • Park users will be diverted via Hoon Hay Road or Lyttelton Street to gain access to Pioneer.
  • There will be some noise disruption during the construction of the new paths and the installation of the trenches and new light poles.
  • We will start work from the Sparks Road end of the park and work back towards Rose Street.
  • See below for an image of the park and the alignment of the path and lighting.
McBeath Avenue / Muirson Avenue Intersection - 12 October 2020

What: Footpath, kerb and channel, road construction – including block paving

Where: Intersection of McBeath Avenue and Muirson Avenue

When: Wednesday 15 October to Friday 26 November – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Full closure of the McBeath Avenue/Muirson Avenue intersection.
  • Closure will impact:
  1. 7 to 10 Muirson Avenue
  2. 24 to 34 McBeath Avenue
  • Roadside parking will not be available outside these properties.
  • Access for affected residents will be via Hoon Hay Road – Smartlea Street – Greenpark Street.
  • Pedestrian access will be maintained but may change on a day to day basis, depending on works.
  • Access to residents’ driveways will be maintained where practical, any work planned across a residents driveway will be brief and at an agreed time.
Download PDF
Sparks Road - 28 September 2020

What: Footpath, kerb and channel, traffic lights

Where: Between 37 and 66 Sparks Road

When: Monday 28 September to Saturday 10 October – hours of work Monday to Saturday, 7am – 6pm. There may some night works required

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • From 7am Monday 28 of September until Saturday 10 October, we will be working in the road shoulder and traffic will still flow via 2 lanes. The lanes will move to allow for our work.
  • On Sunday 4 October between the hours of 6pm and 6am, we will be installing traffic lights outside property numbers 43/41 and 48 Sparks Road. Stop-Go traffic management will be in place for this time.
  • The bus stop outside 50 Sparks Road will be temporarily closed while we undertake this work. An alternative bus stop can be found outside BP service station on Hoon Hay Road.
  • Residents will have access to their driveways, however if there is a short period where we have to restrict access, our supervisor will discuss individual access needs with affected residents directly.
Download PDF
Domain Terrace / Cobham Street / Glynne Crescent - 21 September 2020

What: Temporary road closure

Where: 5 Domain Terrace to 12 Cobham Street and 28 Glynne Crescent to Cobham Street intersection

When: Monday 21 September to Friday 16 October – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Temporary road closure from 5 Domain Terrace to 12 Cobham Street and from 28 Glynne Crescent to the Cobham Street intersection.
  • Closure will impact:
  1. Domain Terrace numbers 1, 2 and 3 – detour via Domain Terrace – Neville Street – Lyttleton Street or Domain Terrace – Lincoln Road. Resident to please park on Cobham Street and access properties via pedestrian walkways between 7am and 6pm.
  2. Cobham Street numbers 2, 8A and 12 – access will be via Cobham Street. Residents to please park on Cobham Street and access properties via pedestrian walkways between 7am and 6pm.
  3. Glynn Crescent numbers 28, 30 34, 37 and 39 – detour via Glynne Crescent – Lyttleton Street. Residents to please park on Glynne Crescent and use pedestrian walkways between 7am and 6pm.
  • Please note, pedestrian access will be maintained but may change on a day to day basis, depending on works.
  • Inside the hours of 7am – 6pm, residents requiring access to their properties where there is no designated pedestrian walkway will be escorted by a crew member to ensure a safe entry/exit to and from their properties.
Download PDF
Greenpark Street / McBeath Avenue Intersection - 21 September 2020

What: Footpath, kerb and channel, road construction – including block paving

Where: Intersection of McBeath Avenue and Greenpark Street (Smartlea Street end)

When: Monday 21 September to Saturday 10 October – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Access to Greenpark Street will be via Muirson Avenue.McBeath Avenue will be reduced to one lane under a priority give way system.
  • Roadside parking will not be available from between house number 57 to 71 McBeath Avenue.
  • Pedestrian access will be maintained but my change on a day to day basis, depending on works.
  • Access to residents’ driveways will be maintained where practical, any work planned across a residents driveway will be brief and at an agreed time
Download PDF
Pablo Place Cul-de-Sac - 21 September 2020

What: Footpath, kerb and channel, road construction – including block paving

Where: Pablo Place

When: Monday 21 September to Saturday 10 October – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • From Monday 21 September to Saturday 10 October, Pablo Place will be closed Monday to Saturday between the hours of 7am to 6pm. Residents will be able to exit their properties up to 9am, from 9am the full road closure will be in place.
  • Residents will have vehicle access to their properties outside the hours of 7am to 6pm.
  • While the road closure is in place parking and pedestrian access for residents into Pablo Place will be via Hoon Hay Road-Muirson Avenue-McBeath Avenue and through the alley way into Pablo Place.
  • There will be no on-street parking available in Pablo Place for the duration of the works.
  • Pedestrian access will be maintained but may change on a day to day basis, depending on works.
Download PDF
Annex Road underpass to Lincoln Road - 14 September 2020

What: Cycleway, footpath, kerb and channel, road construction, drainage network upgrade

Where: Annex Road from the motorway underpass to Lincoln Road

When: Monday 24 August to Monday 26 October – hours of work Monday to Saturday, 7am-6pm

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • From the roundabout to the childcare centre there will be a manned stop/go at a later stage of the works.
  • From the childcare centre to the last hospital access, a single lane will be controlled by traffic-lights. Pedestrians will have a separate access way; cyclists will share the lane with traffic.
  • The road will be closed from the last hospital access to the motorway underpass for vehicles, however a shared path will be available for pedestrians and cyclists.
  • All access points into the hospital will be maintained, exits will be via nominated exits as shown below.
  • There will be parking restrictions in place as shown on the map below in pink.
  • Access to residents’ driveways will be maintained where practical. Any work planned across a resident’s driveway will be brief and at an agreed time.
Download PDF
Domain Terrace - 14 September 2020

What: Cycleway, footpath, kerb and channel, road construction, drainage network upgrade

Where: Domain Terrace - Lincoln Road to Cobham Street

When: Monday 24 August to Monday 26 October – hours of work Monday to Saturday, 7am-6pm

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Two-way traffic will remain with a lane shift in place from Lincoln Road to Cobham Street.
  • Pedestrian access will be maintained but may change on a day by day basis, depending on works.
  • Access to residents’ driveways will be maintained where practical. Any work planned across a resident’s drivewaywill be brief and at an agreed time.
Download PDF
Ferniehurst Street / Woodbank Street Intersection - 14 September 2020

What: Footpath, kerb and channel, road construction – including block paving

Where: Intersection of Ferniehurst Street and Woodbank Street

When: Monday 14 September to Saturday 31 October – hours of work Monday to Saturday, 7am – 6pm

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Stage 1 of the works will involve traffic being controlled by a 3-way traffic light system to enable one lane access to Woodbank Street, Karaka Place and Paikea Place, via Palmside Street.
  1. Road closure – Ferniehurst Street, from 20 Ferniehurst Street to Woodbank Street, closure in place from Monday 14 September, 6am to Monday 5 October, 7pm
  2. Woodbank Street, Karaka Place and Paikea Place residents will need to use Palmside Street to access their properties
  3. No parking from 4 Palmside Street to 1 Karaka Place
  • Stage 2 of the works will involve traffic being controlled by a 3-way traffic light system to enable one lane access to Woodbank Street, Karaka Place and Paikea Place, via Ferniehurst Street.
  1. Road closure – Woodbank Street, from 6 Woodbank Street up to Ferniehurst Street. Closure in place from Monday 5 October, 6am to Saturday 31 October, 7pm
  2. Road closure in conjunction with Stage 2 works – Ferniehurst/Woodbank intersection, daily closure (Monday to Friday – 9am to 4pm) from Monday 5 October to Saturday 31 October
  • Pedestrian access will be maintained but my change on a day to day basis, depending on works.
  • Access to residents’ driveways will be maintained where practical, any work planned across a resident’s driveway will be brief and at an agreed time.
Download PDF
McBeath Avenue / Greenpark Street / Pablo Place - 14 September 2020

What: Footpath, kerb and channel, road construction, drainage network upgrade

Where: Intersection of McBeath Ave/Greenpark St & Pablo Place alley way

When: Monday 24 August Friday 2 October – hours of work will be 7am to 6pm (Monday to Saturday)

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Initially a one-way system will be in place for east flowing traffic (i.e. from McBeath to Greenpark).
  • West bound traffic (i.e. from Greenpark to McBeath) will be detoured via Murison Avenue.
  • A temporary road closure for up to 10 days, between 7am and 6pm, on McBeath Avenue/Greenpark Street corner is required to complete this section of work. We will door knock residents to discuss arrangements for your vehicle and access to your property during the day.
  • The walkway through to Pablo Place will be closed for the duration of the works. Detours for pedestrians and cyclists will be in place via Muirson Avenue, Hoon Hay Road and back onto Sparks Road.
  • All other pedestrian access will be maintained but may change on a day by day basis, depending on works.
  • Impacts to residents’ driveways will be kept to a minimum, any work planned across a resident’s driveway will be brief and at an agreed time.
  • An additional work notice will be provided 7 days prior to the road closure taking effect.
Download PDF
Rose Street / Palmside Street Intersection - 14 September 2020

What: Footpath, kerb and channel, road construction, drainage network upgrade

Where: Intersection of Rose Street and Palmside Street (opposite Centennial Park)

When: Monday 24 August to Friday 25 September – hours of work will be 7am to 6pm (Monday to Saturday)

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Rose Street will be reduced to one lane with traffic light control.
  • Palmside Street will be temporarily closed with access via Ferniehurst Street (off Cashmere Road).
  • Pedestrian access will be maintained but may change on a day by day basis, depending on works.
  • Access to residents’ driveways will be maintained where practical, any work planned across a resident’s driveway will be brief and at a time suitable around individual access needs.
Download PDF
Smartlea Street / McBeath Avenue / Weir Place Intersection - 14 September 2020

What: Footpath, kerb and channel, road construction – including block paving, drainage network upgrade

Where: Intersection of McBeath Avenue, Smartlea Street, Weir Place

When: Monday 24 August to Friday 2 October - hours of work Monday to Saturday, 7am-6pm

Why: To enable the construction of the Nor’West Arc cycleway. Our network of cycleways are making it safer and easier for people to cycle. More people cycling eases the pressure on our roads.

Traffic Impacts

  • Access to McBeath Avenue via Smartlea Street will be closed to all traffic, access will be via Muirson Avenue.
  • Smartlea Street will be reduced to one lane under a priority give way system.
  • From Monday 7 September until Monday 21 September, Weir Place will be closed to vehicles between 7am and 6pm, 5 days a week while we undertake upgrade work across this intersection. We will door knock residents to discuss arrangements for your vehicle and access to your property during the day.
  • Pedestrian access will be maintained but may change on a day by day basis, depending on works.
  • Access to residents’ driveways will be maintained where practical, any work planned across a resident’s driveway will be brief and at an agreed time.
Download PDF