Existing Sites

Springs Road and Marshs Road Intersection Upgrade - 5 November 2021

What: Final road surfacing for new roundabout

Where: Intersection of Springs Road and Marshs Road

When: 14 November to 19 November 2021 NIGHTWORKS

Contact: Isaac Construction - Project Manager: Chris Forde - Email: cforde@isaac.co.nz ∙ Phone: 027 445 0876


We are writing to let you know that we are working towards the final surfacing works of the Springs/ Marshs roundabout.

To do this, Marshs Road East and Marshs Road West will be closed at the intersection with Springs Road for up to 5 nights during off-peak times - from 7pm to 6am.

During this time Springs Road will also be reduced, as required, to one lane with intermittent Stop/Go.

Marshs Road West traffic can detour either via Blakes or Halswell Junction Roads while Marshs East traffic can detour via Fountains and Hodgens Roads.

Road closure notice boards will be erected nearer the time to advise of the works.

A map of the road work area is included on the back of this letter.

Bi-weekly updates for the project will be posted online at the following web address: https://isaac.co.nz/projects/ongoing.

If you have any questions or concerns, or think there is something we should know please contact Chris Forde at Isaacs on cforde@isaac.co.nz or 027 445 0876

Thank you for your patience whilst we carry out this work.

Download PDF
Widening of Blakes Road - 24 June 2021

What: Widening of Blakes Road as part of the construction of the Blakes Road/Shands Road roundabout

Where: Intersection of Blakes Road with Hinterland/Cairnbrae Drivesd

When: 24 June 2021 to 21 July 2021

Contact: Isaac Construction - Project Communications: Jessica Swift - Email: jswift@isaac.co.nz ∙ Phone: 027 207 4631


This is an update to impacted residents advising the current one way system will be in place until the 21st of July 2021 due to unforeseen impacts caused by the weather events over the weekend of the 29th and 30th of May and the ongoing poor weather conditions.

We are writing to let you know that we will be working to widen Blakes Road back towards the intersection of Hinterland/Cairnbrae Drives with Blakes Road. This work involves new shoulder construction to widen the existing road down as far as 46 Blakes Road where the new work will tie into the existing footpath and shoulder on the southern side of Blakes Road.

To do this, we will need to extend the one-way system for up to three weeks. This means:

  • There will be a one-way system in place on Blakes Road for north-bound traffic from property number 46 Blakes Road up to the intersection with Shands Road.
  • Carpenter Drive and Hazelnut Avenue residents are encouraged to use the Hinterland Drive entry/exit to avoid major route impacts.
  • Aberdeen Road and Blakes Road residents from property #46 to #143 (Blakes Road) will need to detour via the north-bound Blakes Road one-way system to Shands Road and back to Trents Road and onto Springs Road.
  • Some stages of the construction works will require manual traffic control for short, intermittent periods of time.
  • Speed restrictions will be in place and we encourage road users to comply with the speed restrictions at all times.
  • Cyclist will be merging with the traffic, please exercise extreme care.

A map of the road work area and detours is included in the downloadable PDF.

Download PDF
Blakes Road Upgrade - 10 May 2021

What: Widening of Blakes Road as part of the construction of the Blakes Road/Shands Road Roundabout

Where: Intersection of Blakes Road with Hinterland/Cairnbrae Drives

When: 17 May 2021 to 07 June 2021

Contact: Isaac Construction - Project Communications: Jessica Swift - Email: jswift@isaac.co.nz ∙ Phone: 027 207 4631


We are writing to let you know that we will be working to widen Blakes Road back towards the intersection of Hinterland/Cairnbrae Drives with Blakes Road. This work involves new shoulder construction to widen the existing road down as far as 46 Blakes Road where the new work will tie into the existing footpath and
shoulder on the southern side of Blakes Road.
To do this, we will need to extend the one-way system for up to three weeks. This means:

  • There will be a one-way system in place on Blakes Road for north-bound traffic from property number 46 Blakes Road up to the intersection with Shands Road.
  • Carpenter Drive and Hazelnut Avenue residents are encouraged to use the Hinterland Drive entry/exit to avoid major route impacts.
  • Aberdeen Road and Blakes Road residents from property #46 to #143 (Blakes Road) will need to detour via the north-bound Blakes Road one-way system to Shands Road and back to Trents Road and onto Springs Road.
  • Some stages of the construction works will require manual traffic control for short, intermittent periods of time.
  • Speed restrictions will be in place and we encourage road users to comply with the speed restrictions at all times.
  • Cyclist will be merging with the traffic, please exercise extreme care.

Please download the PDF for a map of the road work area and detours.

Download PDF
Springs Road and Marshs Road Intersection Upgrade - 13 April 2021

What: Construction of a new roundabout , including cycleways and upgraded road layout

Where: Intersection of Springs Road and Marshs Road

When: 19 April 2021 to 4 October 2021

Contact: Isaac Construction - Project Communications: Jessica Swift - Email: jswift@isaac.co.nz ∙ Phone: 027 207 4631


We are writing to let you know that the Council will begin construction work from the week commencing 19 April 2021 on upgrading the Springs Road and Marshs Road intersection. This will involve beginning the main construction works on a new roundabout to help manage safety and traffic flows in the area.
During the construction works the following traffic management will be in place:

  • Springs Road will have speed reductions in place to manage two-way traffic flows through the
    intersection with Marshs Road.
  • There will be no entry into Marshs Road from Springs Road:
    o Access to Healthy Harvest and Egmont Commercial from Springs Road must detour down Hodgens Road > Fountains Road and back onto Marshs Road
    o Access to Waste Management, Texture Plants and Lush Lawns must detour down Trents Road / Halwells Junction Road > Shands Road and back onto Marshs Road'
  • There will be a one-way systems in place for traffic on Marshs Road heading towards Springs Road
    from Marshs Road property #315 through the intersection to property #348.
  • Some stages of the construction works will require manual traffic control for short, intermittent
    periods of time.
  • Cyclist will be merging with the traffic, please exercise extreme care.

Please download the PDF to find a map of the road work area.

Download PDF
Blakes Road and Shands Road Intersection - 5 March 2021

What: Construction of a new roundabout , including cycleways and upgraded road layout

Where: Intersection of Blakes Road and Shands Road

When: 08 March 2021 to 31 August 2021

Contact: Isaac Construction - Project Communications: Jessica Swift -
Email: jswift@isaac.co.nz ∙ Phone: 027 207 4631

Construction work will start from the week commencing 08 March 2021 on upgrading the Blakes Road and Shands Road intersection. This will involve beginning the main construction works on a new roundabout to help manage safety and traffic flows in the area.

We will also be widening Blakes Road from north west of Hinterland/Cairnbrae Drive, up to the intersection with Shands Road and installing a cycleway and minor changes to the road layout.

  • During the construction works the following traffic management will be in place:
  • Shands Road will have speed reductions in place to manage two-way traffic flows through the intersection with Blakes Road.
  • There will be no entry into Blakes Road from Shands Road, traffic to detour down Trents Road.
  • There will be a one-way system in place on Blakes Road for north-bound traffic.
  • Access will be maintained on Blakes Road from property #169 to #274, lanes will be narrowed and speed reductions will be in place.
  • Some stages of the construction works will require manual traffic control for short, intermittent periods of time.
  • Cyclist will be merging with the traffic, please exercise extreme care.

Please download the PDF document to view the map of the road work area.

Download PDF
Springs Road and Marshs Road Intersection Upgrade - 16 February 2021

What: Construction of a new roundabout , including cycleways and upgraded road layout

Where: Intersection of Springs Road and Marshs Road

When: 01 March 2021 to 31 August 2021

Contact: Isaac Construction - Project Communications: Jessica Swift - Email: jswift@isaac.co.nz ∙ Phone: 027 207 4631


We are writing to let you know that the Council will begin work on 01 March 2021 on upgrading the Springs Road and Marshs Road intersection. This will involve the enabling works (tree removal and fence construction) followed by the construction works involving the installation a new roundabout to help manage safety and traffic flows in the area.
During the enabling works, Springs Road and Marshs Road will remain open in both directions, but with shoulder closures and temporary speed limits in place. A map of the road work area is included on the back of this letter.
Prior to the main construction works taking place, another work notice will be issued outlining the temporary traffic management plan and impacts for residents and stakeholders.

Download PDF
Blakes Road and Shands Road Intersection Upgrade - 16 February 2021

What: Construction of a new roundabout , including cycleways and upgraded road layout

Where: Intersection of Blakes Road and Shands Road

When: 01 March 2021 to 31 August 2021

Contact: Isaac Construction - Project Communications: Jessica Swift - Email: jswift@isaac.co.nz ∙ Phone: 027 207 4631


We are writing to let you know that the Council will begin work on 01 March 2021 on upgrading the Springs Road and Marshs Road intersection. This will involve the enabling works (tree removal and fence construction) followed by the construction works involving the installation a new roundabout to help manage safety and traffic flows in the area.
We will also be widening Blakes Road from north west of Hinterland/Cairnbrae Drive, up to the intersection with Shands Road and installing a cycleway and minor changes to the road layout.
During the enabling works, primarily Shands Road and Blakes Road will remain open in both directions with shoulder closures and temporary speed limits in place. In instances where trees close to the road are being felled, a stop-go system will be in place for short periods of time. A map of the road work area is included on the back of this letter.
Prior to the main construction works taking place, another work notice will be issued outlining the temporary traffic management plan and impacts for residents and stakeholders.

Project Progress

Project Progress - 5 November 2021

Springs Update

  • The final surfacing is due to be done on nights week commencing 14 November 2021.
  • The finishing touches will be done week commencing 22 November 2021.
  • The new roundabout will be open to traffic around the 26 November 2021.

Shands Update

The roundabout is complete.

Project Progress - Week 28 September to 12 October 2021

Shands Blakes Roundabout

The Shands Blakes Roundabout is now complete and fully open.

There is a Temporary speed restriction in place of 60kph untill the permanent 60kph is approved by Selwyn District Council.

Some of landscape planting to be completed on the bund on the North East corner and some greening for cyclists which can only be applied at least a month after the asphalt has been laid.

Spring Marshs Roundabout

On the Springs Marshs Roundabout we are working very hard with a lot of crews to get this work complete by the end of November 2021. Traffic will soon be temporarily using the new alignment on the west side of the roundabout & the new Springs Road centreline while we dig out the east side.

Please remember there is a 30kph speed restriction in place while these works are being undertaken and we ask that you respect the 30kph speed for our workers and the general public safety on the site.

Project Progress - Weeks 20 August - 27 September 2021

Shands/Blakes Roundabout Site – now 100% complete

  • Construction works – 100% complete

Springs/Marshs Roundabout Site – now 65% complete

Traffic Management:

  • Marshs Road reduced to one lane from Texture Plants entry/exit towards Springs Road and Marshs Road from Healthy Harvest entry/exit up to Springs Road
  • Two lane contraflow on Springs Road, speed restrictions in place
  • Springs & Marshs Road reduced to one lane with 4 way stop/go traffic lights off peak (nightworks) for 3 weeks commencing Sunday 26/09/2021. This work is required to install a pipe under Springs Road then construct the new road alignment at the tie ins at both ends of Springs Road
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete
  • Currently working on driveway & gate for north east property

Contract Works:

  • Road construction – 65% complete
  • Drainage works – 95% complete
  • Service Trenching – 100% complete
  • Street lights approx. 75% installed
  • Footpaths 25% complete
Project Progress - Week 29 July - 19 August 2021

Shands/Blakes Roundabout Site – now 85% complete

Traffic Management:

  • Blakes Road reduced to one lane from Aberdeen up to Shands Road (Blakes between Aberdeen & Cairnbrae now back to 2 way)
  • Two lane contraflow on Shands Road, speed restriction in place.
  • Traffic is now running on the West side of Shands Road while we complete the road construction on the East side of Shands Road.
  • Signage in place to ensure no passing of cyclists
  • Shands Road East will be closed during off peak times to complete the hotmix on the roundabout in approx. 2 weeks’ time – exact date to be confirmed and is subject to weather & progress on site. This will be notified by letter drop and VMS electronic notice boards nearer the time.
  • Shands Road West – the access will also be restricted as above.

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 85% complete
  • Private fencing work complete on north west corner
  • Construction of private fencing on north east corner completed

Contract Works:

  • Drainage works – 98% complete
  • Service trenching – 100% complete
  • Road construction – 85% complete
  • Roundabout construction (splitter islands, kerb & channel, central roundabout) – 85% complete
  • Road construction on the East side of Shands Road is nearing completion – the finishing of the basecourse and hotmix in that area has been delayed by the weather & now Covid lockdown – just have to complete the hotmix in that area as soon as we can.
  • As soon as the above has been completed we will construct the roundabout kerb, concrete apron & remaining splitter island & then complete the hotmix wearing course.
  • Blakes Road West and the South side of Blakes East the Chipseal surface has been laid
  • Currently working on north east footpath, table drains, swales & topsoiling of berms when weather suitable
  • Approx. 50% of the street lights have been installed (although the luminaires are not yet available as they are sourced from Europe)

Springs/Marshs Roundabout Site – now 55% complete

Traffic Management:

  • Marshs Road reduced to one lane from Texture Plants entry/exit towards Springs Road and Marshs Road from Healthy Harvest entry/exit up to Springs Road
  • Two lane contraflow on Springs Road, speed restrictions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete
  • Currently working on driveway & gate for north east property

Contract Works:

  • Road construction – 45% complete
  • Drainage works – 90% complete
  • Service Trenching – 100% complete
  • The existing Chorus fibre & copper cables are due to be switched over to the new alignment in the next week.
  • All the new underground HV power cables are now live and all the power poles and overhead wires have been removed
  • Kerb has been poured on South West, North West & Springs South splitter island.
  • Currently digging out the Springs north west, Marsh north west and Marshs north east road areas to subgrade & placing the sub base metal
  • Drainage channel and swale has been completed on the North West corner.
  • Table drains to collect stormwater run-off from adjacent properties on the west side of Springs have now been completed
  • Filling of the footpath on the west side of Springs has started to stabilise these areas from erosion.
  • Stormwater culvert & headwalls have been installed to south west & north east property driveway/entrance ways
  • The new street lights are about to be installed

Blakes Road Widening

  • Construction works – 98% complete
  • Some line marking to be done
  • Topsoil of berms to be done when weather suitable
Project Progress - Week 1 - 28 July 2021

Shands/Blakes Roundabout Site

Traffic Management:

  • Blakes Road reduced to one lane from Aberdeen up to Shands Road (Blakes between Aberdeen & Cairnbrae now back to 2 way)
  • Two lane contraflow on Shands Road, speed restriction in place
  • Manual Stop/go off peak for road dig out on East side of Shands at times
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 85% complete
  • Private fencing work complete on north west corner
  • Construction of private fencing on north east corner currently under way

Contract Works:

  • Drainage works – 98% complete
  • Service trenching – 100% complete
  • Road construction – 85% complete
  • Roundabout construction (splitter islands, kerb & channel, central roundabout) – 70% complete
  • On west side of Shands Road deep lift hotmix has been completed & membrane seal has been applied on the approach & departure to roundabout just waiting for break in weather to lay the wearing course (Temperature has to be 10 degrees & rising for this layer).
  • As soon as the above has been completed Shands Road traffic will be switched over to west side while we complete east side road construction.
  • Working on the basecourse layer on Blakes West & east & getting this ready for the 2 Coat Chipseal & once again hampered by weather
  • Footpath construction on going on 3 of the 4 corners.

Springs/Marshs Roundabout Site

Traffic Management:

  • Marshs Road reduced to one lane from Texture Plants entry/exit towards Springs Road and Marshs Road from Healthy Harvest entry/exit up to Springs Road
  • Two lane contraflow on Springs Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete

Contract Works:

  • Road construction – 35% complete
  • Drainage works – 90% complete
  • Service Trenching – 100% complete
  • The new underground HV cables are due to go live w/c 26/07/21 with the power poles and over head wires to be removed following week.
  • Kerb has been poured on South West corner & currently working on North West kerb.

Blakes Road Widening

  • Construction works – 98% complete
  • Just one driveway & north west corner of Blakes Aberdeen to be sealed.
Week Progress - Week 8-30 June 2021

Shands/Blakes Roundabout Site

Traffic Management:

  • Blakes Road reduced to one lane from #46 Blakes Road (close to intersection of Blakes Road with Cairnbrae/Hinterland) up to Shands Road
  • This has been extended until 21 July to allow the surface to dry out before chip sealing
  • We have been given approval to asphalt the shoulder which we plan to undertake this Friday the 2nd of July 2021, this will enable us to open two lanes of traffic from the Blakes Road/Aberdeen Road intersection back towards Cairnbrae/Hinterland
  • We would like to thank everyone for their patience while we have been working in unfavorable weather conditions to complete this portion of the project
  • Two lane contraflow on Shands Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 85% complete

Contract Works:

  • Drainage works – 95% complete
  • Service trenching – 100% complete
  • Road construction – 75% complete
  • Roundabout construction (splitter islands, kerb & channel, central roundabout) – 55% complete

Springs/Marshs Roundabout Site

Traffic Management:

  • Marshs Road reduced to one lane from Texture Plants entry/exit towards Springs Road and Marshs Road from Healthy Harvest entry/exit up to Springs Road
  • Two lane contraflow on Springs Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete

Contract Works:

  • Road construction – 30% complete
  • Drainage works – 85% complete
  • Service Trenching – 50% complete

Blakes Road Widening

  • Construction works – 92% complete
Week Progress - Weeks 25 May - 7 June 2021

Shands/Blakes Roundabout Site

Traffic Management:

  • Blakes Road reduced to one lane from #46 Blakes Road (close to intersection of Blakes Road with Cairnbrae/Hinterland) up to Shands Road - This has been extended until 23 June to allow the surface to dry out before chip sealing
  • Two lane contraflow on Shands Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 65% complete

Contract Works:

  • Drainage works – 95% complete
  • Service trenching – 99% complete
  • Road construction – 65% complete
  • Roundabout construction (splitter islands, kerb & channel, central roundabout) – 35% complete

Springs/Marshs Roundabout Site

Traffic Management:

  • Marshs Road reduced to one lane from Texture Plants entry/exit towards Springs Road and Marshs Road from Healthy Harvest entry/exit up to Springs Road
  • Two lane contraflow on Springs Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete

Contract Works:

  • Road construction – 20% complete
  • Drainage works – 78% complete
  • Service Trenching – 30% complete

Blakes Road Widening

  • Construction works – 88% complete
Week Progress - Weeks 10 May - 24 May 2021

Shands/Blakes Roundabout Site

Traffic Management:

  • Blakes Road reduced to one lane from #46 Blakes Road (close to intersection of Blakes Road with Cairnbrae/Hinterland) up to Shands Road
  • Two lane contraflow on Shands Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 55% complete

Contract Works:

  • Site clearance and general set up of compound on Shands Road
  • Drainage works – 95% complete
  • Service trenching – 99% complete
  • Road construction – 55% complete
  • New underground HV cables are now live
  • Removal of overhead wires and power poles

Springs/Marshs Roundabout Site

Traffic Management:

  • Marshs Road reduced to one lane from Texture Plants entry/exit towards Springs Road and Marshs Road from Healthy Harvest entry/exit up to Springs Road
  • Two lane contraflow on Springs Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete

Contract Works:

  • Road construction – 20% complete
  • Drainage works – 75% complete
  • Service Trenching – 25% complete

Blakes Road Widening

  • Construction works – 75% complete
Update Progress - Weeks 27 April to 9 May 2021

Shands/Blakes Roundabout Site

Traffic Management:

  • Blakes Road reduced to one lane from Aberdeen Road up to Shands Road
  • Note the current one way system will extend down from Aberdeen Road to #46 Blakes Road from Monday the 17th to enable the progression of our widening works
  • Two lane contraflow on Shands Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 35% complete

Contract Works:

  • Site clearance and general set up of compound on Shands Road
  • Drainage works – 85% complete
  • Service trenching – 97% complete
  • Road construction – 40% complete

Springs/Marshs Roundabout Site

Traffic Management:

  • Marshs Road reduced to one lane from Texture Plants entry/exit towards Springs Road and Marshs Road from Healthy Harvest entry/exit up to Springs Road
  • Two lane contraflow on Springs Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete

Contract Works:

  • Road construction – 20% complete
  • Drainage works – 45% complete

Blakes Road Widening

  • Construction works – 55% complete
Update Progress - Weeks 12-26 April 2021

Shands/Blakes Roundabout Site

Traffic Management:

  • Blakes Road reduced to one lane from Aberdeen Road up to Shands Road
  • Two lane contraflow on Shands Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 25% complete

Contract Works:

  • Site clearance and general set up of compound on Shands Road
  • Drainage works – 80% complete
  • Service trenching – 90% complete
  • Road construction – 30% complete

Springs/Marshs Roundabout Site

Traffic Management:

  • Shoulder closures in place

Note:

  • We will have two lane contraflow and speed reductions in place from 19/04/2021 on Springs Road
  • Marshs Road will be one lane south bound from south of the Texture Plants entrance way to Springs Road from 19/04/2021, traffic to detour via Shands Road
  • Marshs Road will be one lane north bound from outside the Fruit and Vege shop to Springs Road from 19/04/2021, traffic to detour via Hodgens Road then Foundations Road

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete

Contract Works:

  • Road construction – 12%
  • Drainage works – 15%

Blakes Road Widening

  • Construction works – 45% complete
Update Progress - Weeks 21 March 2021 - 11 April 2021

Shands/Blakes Roundabout Site

Traffic Management:

  • Shoulder closures in place
  • Blakes Road reduced to one lane from Aberdeen Road up to Shands Road
  • Two lane contraflow on Shands Road, speed reductions in place
  • Signage in place to ensure no passing of cyclists

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 25% complete

Contract Works:

  • Site clearance and general set up of compound on Shands Road
  • Drainage works – 70% complete
  • Service trenching – 50% complete
  • Road construction – 30% complete

Springs/Marshs Roundabout Site

Traffic Management:

  • Shoulder closures in place

Note:

  • We will have two lane contraflow and speed reductions in place from 19/04/2021 on Springs Road
  • Marshs Road will be one lane south bound from south of the Texture Plants entrance way to Springs Road from 19/04/2021, traffic to detour via Shands Road
  • Marshs Road will be one lane north bound from outside the Fruit and Vege shop to Springs Road from 19/04/2021, traffic to detour via Hodgens Road then Foundations Road

Enabling Works:

  • Tree removal and stump grinding – 100% complete
  • Fence removal and construction of new boundary fencing – 80% complete

Contract Works:

  • To start week commencing 19/04/2021

Blakes Road Widening

  • Construction works – 15% complete
Project Progress - Week 15-21 March 2021

Shands/Blakes RAB Site

  • Completion of tree removal and stump grinding
  • Roading digout complete at the SE corner of the site
  • Soakage pits installed
  • Survey setout (ongoing)
  • Potholing undertaken
  • Starting digouts in NE and SW corners of site
  • Starting ducting
  • Start boundary fencing

Springs/Marshs RAB Site

  • Completion of tree removal and stump grinding
  • 50% complete for boundary fence installation
Project Progress - Week 8- 14 March 2021

Isaac Construction mobilised to site during the week commencing 01 March 2021 and now occupy the designated compound/laydown and site office spaces off Shands Road. We also installed the shoulder closures at both the Shands/Blakes and Springs/Marshs sites to make a start on the enabling works.

Enabling works started at both roundabout sites with Treetech making rapid progress across both roundabout sites by tree felling, chipping and stump grinding which has resulted in quite a different look at both the sites. The fencing has also started at both sites, with a large portion of the fencing having been completed at the Springs/Marshs site.

Drainage works were started on the Shands/Blakes site from week commencing 08 March 2021 and to date we have installed 2 large soak pits, as well as making a start on the road dig out on the southern side of the Shands/Blakes site.